Principle
(Original Document)
Introduction
When installing the INTERBUS it is necessary first of all to define the physical context of the project into which it is to be integrated (rack, mains supply, processor, modules or devices, etc.) and then carry out the required software installation.
Its software installation is carried out using the different editors of Control Expert:
The order of the different installation phases is predefined; nevertheless, it is possible to modify the order of certain phases (for example to begin with the configuration phase).
Installation principle
The table below presents the different installation phases of the INTERBUS.
Phase
Description
Mode
Declaration of variables
Declaration of IODDT type variables for application-specific type modules and project variables.
Local (1)
Project programming.
Local (1)
Declaration of modules.
Local
Configuring module channels.
Entering the configuration parameters.
Declaring the bus configuration using the CMD Tool software and generating the *.SVC text file
Association
Associating IODDTs with the configured modules (variable editor).
Local (1)
Generation
Generating the project (analyzing and editing links).
Local
Transfer
Transferring the project to the PLC.
Connected
Project debugging using debug screens, animation tables, CMD software.
Connected
Modification of program and adjustment parameters.
Constituting the project folder and printing the relevant information.
Connected (1)
Visualizing the information necessary for supervisory control of the project.
Connected
Project and module diagnostics.
Key
(1)
These various phases can also be carried out in the other mode.